Each change package is assumed to be installed in production (and change its status to INS/BAS) some day. The date entered during package creation is the actual planned install date. But with package update (U7) you can change it again, typically to shift the date to some other (later) date. The idea of that is that it allows you to change your initially planned date (during package create) to somewhere later on. Because while the package content is being developed, it turns out that the date that was originally scheduled is too early. So far no problem ...